+1

cf.  

"An open IMA
describes the state of a Web Service
operation from the point that a request-response IMA starts execution
until an
associated <reply> activity
completes successfully. " (my emphasis)

"The <receive>
activity completes when the message arrives."

"In the request-response case, the invoke
activity completes when the response is received. "

etc.

Alex Yiu wrote:
 

  

Hi all,

  

About the "complete" wording in section 5.5 in the context of "Fix
description of abnormal process completion" issue discussion, I have
crossed checked with section "11.6.2. Link Semantics" (about
<flow> and <link>). The following phrases are used:

  "When activity A completes,
the following steps MUST be performed to determine the effect
of the links on other activities: ..."

  
(I guess that may open up another question for clarification: when an
activity such as <invoke> faults, would it be considered
completed in the context of links evaluation? My guess is no. But, I
cannot find any explicit text so far. Anyhow, that would be another
issue.)

  

Anyhow, in order to avoid similar guess work from readers, I guess it
may be to say the following in the proposal of Issue 15: 

  The process ends normally when the main activity of the
process completes without propagating any fault.

  
  

  

Thoughts?

  

Thanks!

  

  

Regards,

Alex Yiu

  

  

  Submitter's proposal:
    
Change paragraph in Section 5.5 FROM: 

    A business process instance ends either normally or
abnormally. The
process ends normally when the main activity of the process completes.
The process ends abnormally if either:
      
        
a fault reaches the process scope, regardless of whether it
is
handled or not (see section 10.10. Immediately Ending a Process –
Exit), or 

        
the process instance is explicitly ended by an exit
activity
(see section 10.10. Immediately Ending a Process). 

      
    
    
TO: 

    
      
A business process instance ends either normally or
abnormally.
The
process ends normally when the main activity of the process completes.
The process ends abnormally if either: 

      
        
a process level (explicit or default) fault handler
completes
or 

        
the execution of a process level fault handler itself
faults
(the effect of this particular case is similar to an <exit>
activity or 

        
the process instance is explicitly ended by an exit
activity
(see section 10.10. Immediately Ending a Process).