Issue 193 - Proposed Resolution

From
Prasad Yendluri <>
Date
2005-09-26T20:53:29+00:00
ID
Thread
Issue 193 - Proposed Resolution
I propose that we resolve issue 193 the following way:

In section "12.6.1 Link Semantics" add the following text:

"Note
that in order to avoid violating control
dependencies, evaluation of the join condition is performed only after
the status of all incoming links has
been determined."

immediately following the sentence,

 

If an activity that is ready to start in this
sense has
incoming links, then it does not start until the status of all its
incoming
links has been determined and the (implicit or explicit) join condition
associated with the activity has been evaluated. 

The updated paragraph will read as follows:

If an activity that is ready to start in this sense has
incoming links, then it does not start until the status of all its
incoming
links has been determined and the (implicit or explicit) join condition
associated with the activity has been evaluated. Note that in
order to avoid violating control
dependencies, evaluation of the join condition is performed only after
the status of all incoming links has
been determined.

Thanks, 

Prasad