I do not see anything in the OASIS process that says a TC must have a
public review BEFORE approving a spec as a CD by the TC. From the
process:
------------------------
(a). Approval of a Committee Draft
Upon completion of a specification the TC may approve the work as a
Committee Draft. The approval of a Committee Draft shall require at
least 2/3 of the total membership of a TC voting to approve and no more
than 1/4 voting to disapprove.
OASIS TC Administration must be notified at the completion of any ballot
to approve a Committee Draft, regardless of the outcome of the ballot.
The name of a Committee Draft may not include any trademarks or service
marks not owned by OASIS. The Committee Draft must use the
OASIS-approved document templates and naming, and must include the OASIS
copyright.
--------------------------