Suggested DITA 1.3 errata schedule
Date
Milestone
Dependencies
5 July 2016
Test current build process. Does it meet file
naming requirements as noted by Chet?
Waiting on info from Chet
29 July 2016
Complete work on content model generation
Complete work on SEO and Google analytics
1 - 5 August 2016
Build draft DITA 1.3 errata for TC review
8 - 12 August 2016
Internal TC (DITAweb) review of errata (5
days)
15 - 19 August 2016
Build Committee Draft Specification (5 days)
Tuesday, 23 August 2016
Adopt corrections (and updated spec) as a
Committee Draft Specification; request 15-day public review
23 August - 5 September 2016
OASIS staff prepares materials for 15-day
public review (14 days)
6 - 20 September 2016
15-day public review
21 - 26 September 2016
Editors respond to 15-day public review
comments (4 days)
Tuesday, 27 September 2016
TC approves DITA DITA 1.3 errata
27 September - 14 October 2016
OASIS staff prepare DITA 1.3 errata for
publication (14 days)
Monday, 17 October 2016
TC Admin announces DITA 1.3 errata
--
Best,
Kris
Kristen James Eberlein
Chair, OASIS DITA Technical Committee
Principal consultant, Eberlein Consulting
www.eberleinconsulting.com
+1 919 682-2290; kriseberlein (skype)
← Prev in month
← Prev in thread
Next in thread →
Next in month →